Submitting Status from Project Data
This Document can be found in the following categories:
The project manager can make changes on the Project Data sheet
to fields in one or more projects, set the As Of date, select cells
in those rows, and use DATABASE>SUBMIT STATUS to report
status.
Since milestones are not present on Project Data, this method should be
used only if milestones are NOT being tracked or there has been no
change to milestone dates since the last report,
Projects do NOT have to be checked out. A user can submit status
for a project if:
- The user has Project Manager rights to the project, or Project
Edit or higher rights to the node of the selected project, and the
selected node is not checked out by someone else, or
- The project node is checked out by the current user.
(Although any field on the Project Data sheet can be changed by
a project manager during a PDWare session, only the standard
status fields and fields defined as editable by an
administrator in the Status Optional
Fields list will be saved to the database when status is
submitted.)
POS (Project Objective Statement) and Status Notes can be edited
directly in the cell or by right click in a cell on the project row
and selecting menu Show Status Comments to launch a dialog with
both fields.
When all edits have been entered, select the projects (single or
multiple row selection) and select the DATABASE>SUBMIT STATUS
menu.