Schedule the Project

This Document can be found in the following categories:

Select one of the schedule commands from the Scheduler menu

Image

Image Image

If 10 day tasks have been entered, all with the same start and finish dates, the Gantt view looks like the screen shot below.

Image

Reschedule task dates

This schedule method delays the start of tasks to the work day after the finish of all predecessors. It does not remove float, that is it does not move the start earlier if all predecessors finish more than one day before the task start.

Image Task 3 start date was set to 30Dec2009. Reschedule task dates moves Task 3 and all its successors later in time.

Image

Compress schedule

This schedule method does remove float, that is it does move the start earlier if all predecessors finish more than one day before the task start.



Image