Field
|
Description
|
|
Outline
|
Locked: "+" and "-" outline symbols are in
summary task rows.
"+" expands to the next level of subtasks
below the summary.
"-" hides all subtasks below the
summary.
|
|
Change Flag
|
Locked: "N" means the task or row was
created in the current WBS session and has not been saved to the
database.
"C" means a change has been made to the
value of at least one field of the task. Changes include row
position, subtask level, dependency relationships.
|
|
Row #
|
Locked: Task row number in the WBS
table(s).
|
|
Task Name
|
Free form: User defined task name. These
names should be unique but uniqueness is not enforced.
|
|
Duration
|
Numeric entry: Duration of the task
in work days (5 days per week).
If the Start date is changed, the finish
date is calculated by adding duration to the start date.
If the Finish date is changed, the
duration is calculated as the difference between start and
finish.
|
|
Start
|
Date entry: Start date of the
task.
|
|
Finish
|
Date entry: Finish date of the
task.
|
|
Task ID
|
Calculated: The outline type summary index
of a task, e.g. 1.1.1 or 2.3.5.6.
|
|
Lead
|
Free form: The name of team member who is
responsible for the task.
|
|
Baseline Start & Finish
|
Display: If a project baseline is
taken in PDWare Portfolio and there is a WBS plan, the task dates
are captured as the named baseline. Baselines are usually given a
name appropriate to the phase gate at which the baseline is
authorized.
When a WBS is opened, the current (most
recent) baseline is used to populate task baseline
dates.
|
|
Work
|
Calculated: The total defined work effort
of all resources required for the task during the current PDWare
"Get Data" periods.
|
|
Actual
|
Display: Actual work effort tracked
to tasks in the PDWare iTeam product are displayed in this
field.
|
|
Baseline
|
Display: The current baseline
resource plan work effort in full time equivalent work periods (as
defined by the Get Data parameters).
|
|
% Complete
|
Controlled entry: The user can enter
any value from 0 to 100% to capture the approximate amount of work
done on the task (assuming a constant level of effort over the task
duration).
|
|
State
|
List field: Select a value from a drop
down list; (empty), Not started, Started, Complete.
|
|
Comment
|
Free form: Text entry.
|
|
Predecessors - Successors
|
Controlled entry: The user can enter
row numbers of predecessor or successor tasks to create dependency
relationships.
Invalid relationships are cleared
automatically.
|
|
PMLink
|
Controlled entry: Links the task in WBS to
a phase or milestone in PDWare Portfolio.
Values must be of the form "P01" to "P15"
or "M01" to "M30".
|
|
Field1 - 60
|
Free form: May be displayed and used
at the user's discretion.
|