Right click period value commands on sheet Team

This Document can be found in the following categories:

For the team member:

Availability

The current forecast on the Effort Forecasts sheet in PDWare Portfolio for the assignment of the team member to this project

Work effort required

The sum of all task assignment work by period

Satisfied work effort

The sum of all task assignment work by period that can be satisfied by the team member availability

Unsatisfied work effort

The sum of all task assignment work by period that cannot be satisfied by the team member's availability  (Shortfall)

Unused availability

Availability not used/needed by task assignment work

Utilization

Work divided by availability expressed as a percent