Right Click Commands
This Document can be found in the following categories:
|
Insert assignments
(WBS, Task Usage, Team)
|
Select one or more resources on the Team sheet
or one or more tasks on the WBS or Task Usage sheets; right click
in the selection; select one or more objects from the Select
dialog.
A row is created on the Work sheet for each
task-resource combination specified.
Note: Work assignments cannot be created for
milestones or for summary tasks.
|
|
Move selection
(WBS)
|
In the Move selection dialog, enter the row
number below which the selected rows are to be moved.
If the selection is a set of contiguous cells
in the row number column, a right click in the selection
immediately launches the Move selection dialog.
Otherwise, the right click Move selection command must be
selected from the right click menu list.
|
|
Insert rows
(WBS)
|
For each row selected, insert an empty row
above the top selected row.
If three contiguous rows are selected, three
empty rows will be created immediately above the top selected
row.
|
|
Delete
(WBS, Task Usage, Work)
|
Delete the selected records from the plan. The
delete does not take permanent effect until the WBS plan is saved
to the database.
|
|
Insert column
(WBS)
|
Insert selected optional columns immediately
to the left of the current selection
|
|
Define column
(WBS)
|
Define the format, width, horizontal alignment
and title of WBS columns (fields).
|
|
Remove column
(WBS)
|
Remove the selected optional columns from the
display on the WBS sheet.
|
|
Remove filter
(All)
|
Removes all filters on the active sheet. If
the sheet is one of the three WBS-type sheets, the filter is
removed from all of them.
|
|
Show state deviations
|
If checked, State and % Complete cells
inconsistent with each other or with the task start and finish
dates are highlighted with red fill color.
If the State or % Complete columns are not
showing, they are automatically displayed.
See the section below on managing State and %
Complete for additional features.
|
}}}}