Enter sub-tasks / milestones

This Document can be found in the following categories:

Tasks are created by entering a task name in an empty row. The start and finish date are set to the current date and the duration is set to 1 (day) by default.

Dates and Duration

If you change the duration or the start date, the duration number of workdays (5 days per week) is added to the start date to create a new finish date.

If you change the finish date to a value later than the start date, the duration is recalculated to be the number of workdays between start and finish. If the finish date is earlier than the start date, the start date is set equal to the finish date and the duration is 1 day.

Milestones

To change a task to a milestone, just change the duration to zero (0). The finish date cell for a milestone is locked; if the start date is changed, the finish date is set to the same date.

Image