Enter sub-tasks / milestones
This Document can be found in the following categories:
Tasks are created by entering a task name in an empty row. The
start and finish date are set to the current date and the duration
is set to 1 (day) by default.
Dates and Duration¶
If you change the duration or the start date, the duration
number of workdays (5 days per week) is added to the start date to
create a new finish date.
If you change the finish date to a value later than the start date,
the duration is recalculated to be the number of workdays between
start and finish. If the finish date is earlier than the start
date, the start date is set equal to the finish date and the
duration is 1 day.
Milestones
To change a task to a milestone, just change the duration to
zero (0). The finish date cell for a milestone is locked; if the
start date is changed, the finish date is set to the same
date.