Project Manager Adds Team Members
This Document can be found in the following categories:
If there are no
Effort Forecast assignments for the
project or you need skills or people not currently assigned, click
the Add Team Members WBS
toolbar button.
Select the organization from which you need resources; select the
people or skills you need; click the Add button. When done, click
the Close button.
An assignment is created on the PDWare Portfolio
Effort
Forecasts sheet for each skill or resource added; effort values
are left empty (i.e. no forecast effort).
The same resources/skills are added to the Team sheet with no
availability.
You create availability for team members with the Convert ETC to
forecast command.