To request a resource be removed from your project team
This Document can be found in the following categories:
- Delete all work effort for that resource on the Work Plan
sheet.
- Click the Request this Resource Plan toolbar button. This will
"request" zero level of effort from the resource, signaling to the
resource
manager that the resource is not needed on the project during
the zero level of work periods