Set a Project Phase Baseline

This Document can be found in the following categories:

Select one or more projects that have exactly the same phase names, right click on the selection, and select the Submit Baseline command.

Image

This command is available only if the selection is in the label area on the Project Summary sheet.

It executes the following steps for each selected project:

Copies current forecast demand for each resource and skill assignment to the associated baseline record.

Presents a dialog in which the user selects the phase name for the baseline.

Saves the baseline to the database.

Executes the Database>Submit Status with Baseline to capture all project fields from Project Data and the current milestone dates and names.

If the baseline name dialog is cancelled or an invalid name is chosen, the Forecast to Baseline portion of the operation remains in effect but nothing is written to the database. If the module is then closed, the "Save Baseline?" message appears.


"Yes" to this message does NOT submit project status to the database.