Committed Assignments
This Document can be found in the following categories:
If the PDWare administrator has defined one or more effort
states as "committed" in the database, users can apply the state to
assignments. Users have the option to allocate Committed
Assignments before all other assignments.
The effect of using this feature is that committed demand on a
lower priority project may be satisfied before demand for the same
resource on a higher priority project. Committed
Assignments that exceed the capacity of the resource are
highlighted the same as any other assignment.
Note: Get the name of the "committed" effort state from your PDWare
administrator.
To set assignment state to "Committed":
- Select cells in one or more Effort Forecasts rows.
- Right click in the selection and click COMMIT ASSIGNMENT.
This sets the Effort State field to the first committed state in
the Effort State list. An alternative method is to use the Edit
Assignment dialog and select the committed effort state in the
drop down list.
Note: The committed state has no effect on Allocation
Calculation until the Allocate Committed First option is set in
the Tools menu.
To apply the committed state to Allocation Calculation:
- Select TOOLS>ALLOCATE COMMITTED FIRST.
If this menu item is checked, Committed
Assignments are allocated before other assignments. If it
is not checked, effort state is ignored in the calculation
procedure.
To set the default state of the Allocate Committed First menu:
- SelectTOOLS>OPTIONSto open the Options dialog.
- Click the Default Settings tab.
- Check the Default Allocate Committed First checkbox.
Assignments to external projects
If you select a sub node on the project OBS (tree) in the Get Data
dialog and check the Include All Projects for Selected Nodes
checkbox under the resource OBS, any assignments to projects from
other than the selected node are considered "external".
Resources can be external (check Include All Resources for Selected
Nodes) but these features do not apply to assignments of external
resources unless the project is external as well.
All external records on project, resource, and Effort
Forecasts sheets are highlighted by italic font in most (but
not all) PDWare modules. Exceptions include BFA and FEX.
To automatically set the committed state on assignments to external
projects:
- Select TOOLS>OPTIONS to open the Options dialog.
- Click the Default Settings tab.
- Check the Default External Effort to Committed checkbox.
To set the committed state on assignments to external projects:
- SelectTOOLS>COMMIT EXTERNAL ASSIGNMENTS.
This command is a toggle; it sets and removes the state on the
assignments.