Capacity Model Factors

This Document can be found in the following categories:

Min Unutil

Specify the minimum unutilized capacity the Autocalc will look at. Only when unutilized capacity is greater than Min Unutil will capacity be reduced.

If Min Unutil is zero (0), all unutilized capacity will be reduced. If Min Unutil is .3 (30%), a resource 60% utilized will have capacity reduced; a resource 75% utilized will have no capacity reduction.

Change

Target change to total capacity (FTE or Cost). Entering a value here causes an automatic calculation (Autocalc) of a model.

If the value is 0 (no change in total capacity), unutilized capacity will be used to satisfy Demand Shortfall.

The result of this automatic calculation appears in the grid as percent increases or decreases in capacity. Where allocation for a node-skill is to be increased but no resources in the node with that skill has availability an absolute (positive) value will be present. This is a FTE capacity increase.

Change Example

If there is more demand shortfall than unutilized capacity and the change value is the positive difference between them (3.5 in the screen shot below), 100% of portfolio demand will be met.

If the change is -10.6, unutilized will drop to 20 and demand shortfall will be unchanged.

If the change is -40.6, unutilized will drop to 0 and demand shortfall will increase to 44.1. In this case resources allocated to the projects at the bottom of the prioritized project list will have their capacity reduced thereby increasing shortfall.

Image

Enter a value in the Change cell.

Image